Beta: Parallel tracks are in beta. They are being turned on team by team, so they may not be available on your team yet.
When a campaign mixes email and LinkedIn steps, leads move at the pace of the slowest channel. Email has more sending capacity than LinkedIn, and LinkedIn steps go through a single LinkedIn account, so a lead can wait days or weeks before the next touchpoint. Call tasks done late block the following steps in the same way.
With a Parallel tracks block, you split your sequence into two tracks that run at the same time, for example one track for email and one for LinkedIn. The LinkedIn track moves at its own pace and no longer holds back your emails.
Limitations
Parallel tracks are available on the Multichannel and Enterprise plans.
A Parallel tracks block has two tracks: Track 1 and Track 2.
You can add several Parallel tracks blocks in the same campaign.
You cannot add a Parallel tracks block inside a track.
A lead continues after Join only once both tracks are done.
Add parallel tracks to your sequence
Phase 1: Add a Parallel tracks block
In your campaign, open Sequence and click Add step where you want the tracks to start.
Open the Conditions tab and select Parallel tracks, described as "Run steps on separate tracks, at the same time".
Phase 2: Add steps to each track
Each track runs independently, at the same time. A track can contain conditions.
Under Track 1, click Add step and add the steps for one channel, for example your emails.
Under Track 2, click Add step and add the steps for the other channel, for example a LinkedIn invitation and a LinkedIn message, or your call tasks.
Phase 3: Continue the sequence after Join
Join is where the two tracks meet again. The lead continues once all tracks are done.
Below Join, add the steps every lead should get after both tracks.
✅ Verify: the block shows Parallel tracks with "Each track runs on its own clock", then Track 1 and Track 2, then Join when all tracks are done.
Practical example
Your campaign has three emails, a LinkedIn invitation and a LinkedIn message. Add a Parallel tracks block at the start of the sequence. Put the three emails in Track 1, and the LinkedIn invitation and message in Track 2. The emails go out on schedule, while the LinkedIn steps wait for LinkedIn capacity. Below Join, add the steps you want every lead to get once both tracks are done.
Troubleshooting & pitfalls
Issue: Parallel tracks is not in the Conditions tab
Root cause: Parallel tracks are in beta and are being turned on team by team. They are also only available on the Multichannel and Enterprise plans.
Fix: Check that your team is on the Multichannel or Enterprise plan. If it is, parallel tracks are not turned on for your team yet.
Issue: You cannot add Parallel tracks inside a track
Root cause: A Parallel tracks block cannot be added inside another Parallel tracks block.
Fix: Add a second Parallel tracks block below Join instead.
Issue: A lead does not move past Join
Root cause: One of the two tracks is not done for this lead yet, for example a LinkedIn step still waiting for capacity or a call task not done.
Fix: Check the lead's progress in both tracks and complete any pending task. The lead continues once both tracks are done.
If your case is different
If you want to send leads down different paths based on what they do or who they are, see How to use conditions in your campaign sequence.
If you want to understand how lemlist orders and processes the steps of a sequence, see Understand campaign sequencing in lemlist.